- Google has signed a power purchase agreement with Quaise Energy for 50 MW of superhot geothermal electricity from Project Obsidian in Central Oregon, with deliveries expected as early as 2030.
- The project is estimated to cost approximately $350 million, while media reports value the electricity agreement at more than $500 million. The companies have not publicly disclosed the contractual pricing.
- The partnership highlights Google's strategy of securing reliable, carbon-free electricity for its expanding data-center infrastructure as artificial intelligence increases long-term power demand.
Google is expanding its long-term energy strategy through a new geothermal agreement with Quaise Energy, securing access to 50 megawatts of electricity from a planned superhot rock geothermal facility in Central Oregon. The agreement reflects a growing priority among major technology companies: securing reliable, around-the-clock electricity for data centers as artificial intelligence workloads increase pressure on power infrastructure and electricity markets.
Google Secures a Long-Term Geothermal Power Supply
Under the agreement announced on November 17, 2026, Google will purchase 50 MW of electricity from Quaise Energy’s Project Obsidian, a planned geothermal development in Central Oregon. Deliveries are expected to begin as early as 2030, with the electricity intended to support Google’s existing data-center operations in The Dalles, Oregon, and the surrounding region.
The financial scale of the agreement is significant. The project is estimated to require approximately $350 million in development costs, while The Wall Street Journal has reported that the power purchase agreement is worth more than $500 million. However, the companies have not disclosed the electricity price, contract duration or detailed payment structure in their official announcement. The reported valuation should therefore be distinguished from a publicly confirmed contract figure.
For Google, the agreement provides a potential source of dependable electricity that does not rely on intermittent weather conditions. Unlike solar and wind generation, geothermal facilities can produce power continuously when properly developed and operated. This characteristic makes geothermal energy particularly relevant to data centers, which require consistent electricity to support cloud services, AI training and other computing operations.
Quaise’s Superhot Rock Technology Targets a New Geothermal Market
Project Obsidian is designed to access underground rock temperatures exceeding 572°F, using heat from deep geological formations to generate electricity. The development’s initial phase will rely on conventional drilling technology to reach superhot geothermal conditions. Quaise plans to introduce its millimeter-wave drilling technology in a subsequent phase, using a gyrotron-based system designed to vaporize extremely hard rock and reach greater depths.
The company’s approach is intended to overcome one of the principal limitations of conventional geothermal energy: the availability of suitable underground reservoirs. Traditional geothermal facilities are generally concentrated in locations with accessible underground heat and water resources. Superhot rock systems aim to expand the potential geographic reach of geothermal generation by accessing much deeper and hotter geological formations.
However, the technology remains at an early stage of commercial development. The ability to drill efficiently at extreme depths, maintain stable underground reservoirs and generate electricity economically at scale has yet to be demonstrated across a fully commercial operation. Project Obsidian is therefore an important test of whether superhot geothermal energy can move beyond experimental development and become a commercially viable source of electricity.
AI Infrastructure Is Reshaping Technology Companies’ Energy Strategies
The agreement also illustrates how the expansion of artificial intelligence is changing the relationship between technology companies and energy providers. Data centers require substantial and increasingly continuous electricity supplies, while grid connections, transmission infrastructure and power-generation capacity can take years to develop. Securing long-term electricity agreements has consequently become an important part of infrastructure planning for major cloud and AI companies.
Google already has an established geothermal portfolio, including partnerships with other developers such as Fervo Energy. The Quaise agreement adds another technology pathway to its energy strategy, with the potential to provide firm, carbon-free electricity alongside existing renewable-energy procurement. According to Quaise’s announcement, the project is also expected to support construction employment and permanent technical positions in Central Oregon.
The broader commercial implications extend beyond Google. If Project Obsidian demonstrates that superhot geothermal generation can operate reliably and competitively, it could create opportunities for other data-center operators, utilities and industrial electricity consumers seeking dependable low-carbon power. Nevertheless, construction costs, drilling performance, transmission requirements and regulatory approvals will determine whether the model can be replicated at larger scale.
Looking ahead, the key milestones will be the development of Project Obsidian, successful drilling operations and the ability to begin electricity deliveries by 2030. For Google, the agreement represents a long-term effort to secure the energy needed for its expanding computing infrastructure. For Quaise, it provides an important commercial partnership that could help validate a technology still facing substantial engineering and financial challenges. The wider energy market will be watching whether superhot geothermal can become a meaningful contributor to the electricity supply required by the global AI economy.
Comparison, examination, and analysis between investment houses
Leave your details, and an expert from our team will get back to you as soon as possible
* This article, in whole or in part, does not contain any promise of investment returns, nor does it constitute professional advice to make investments in any particular field.
To read more about the full disclaimer, click here- fidji
- •
- 5 Min Read
- •
- ago 34 seconds
SKN | Skydance Restructures Film Leadership at Paramount and Warner Bros
Skydance Establishes Studio Leadership Structure Skydance has announced a series of leadership appointments across Paramount Pictures and Warner Bros Pictures,
- ago 34 seconds
- •
- 5 Min Read
Skydance Establishes Studio Leadership Structure Skydance has announced a series of leadership appointments across Paramount Pictures and Warner Bros Pictures,
- sagi habasov
- •
- 8 Min Read
- •
- ago 3 minutes
SKN | SpaceX Targets a New AI Infrastructure Market as Orbital Computing Moves Toward Commercial Development
SpaceX is positioning itself to become a significant participant in the rapidly expanding artificial intelligence infrastructure market, with ambitions
- ago 3 minutes
- •
- 8 Min Read
SpaceX is positioning itself to become a significant participant in the rapidly expanding artificial intelligence infrastructure market, with ambitions
- orshu
- •
- 7 Min Read
- •
- ago 4 minutes
SKN | South Korea’s KOSPI Falls Below 5,000 for the First Time Since February as Market Pressure Intensifies
South Korea’s equity market experienced a significant setback on November 17, with the KOSPI Composite Index falling below the
- ago 4 minutes
- •
- 7 Min Read
South Korea’s equity market experienced a significant setback on November 17, with the KOSPI Composite Index falling below the
- orshu
- •
- 7 Min Read
- •
- ago 2 hours
Microsoft Expands AI Model Portfolio With New Coding and Cybersecurity Tools to Challenge OpenAI and Anthropic
Microsoft is expanding its artificial intelligence strategy with a new generation of specialized models for software development and cybersecurity,
- ago 2 hours
- •
- 7 Min Read
Microsoft is expanding its artificial intelligence strategy with a new generation of specialized models for software development and cybersecurity,